The concrete slab for the third floor was completed this week at the St. Lawrence Condominiums. The eastern portion of[…]
Read more
Construction information for 158 Front Street East
This site provides construction information and updates for the St. Lawrence Condominium project at 158 Front Street East, developed by Cityzen and Fernbrook Homes.
The concrete slab for the third floor was completed this week at the St. Lawrence Condominiums. The eastern portion of[…]
Read moreCrews will be on site tomorrow, Saturday, November 23 from 9 am. They will be taking apart forms form already[…]
Read moreThe public art installation on the hoardings at 158 Front is underway. Artist Erin McCluskey and her team was busy today[…]
Read moreThe creation of the public art on the hoardings is set to get underway this week. We expect that artist Erin[…]
Read moreWork at 158 Front Street East was slowed this week by snow and record-breaking cold. However, concrete work resumed yesterday[…]
Read moreWork has been progressing steadily on the west site of the project in past week. The first section of the[…]
Read moreAfter review and discussion with the 158 Front Construction Liaison Committee and the project development team, the artist Erin McCluskey[…]
Read more