Saturday Work at 158 Front St. East, October 19, 2019

Crews will be on-site at 158 Front Street East, tomorrow, Saturday, October 19, from 9 am through the afternoon.

They will taking apart forms from concrete sections that have fully set. They will be extending one of the utility lines into the site and placing in its permanent location to service the future St. Lawrence Condominiums.

There will be other housekeeping tasks on site through the day.

Concrete pouring and forming will resume on Monday, October 21.

Looking up and west, from the complete 2nd floor slab, to the in progress 3rd and 4th floors.