Midweek construction update, October 16, 2019

Today, October 16, was a rain day. Some trades were on site but there was no concrete work.

The first section of the 4th floor of the St. Lawrence Condominiums has been completed. The next phase of work, over the coming 10 days, will aim to see the 3rd floor slab completed in the eastern section of the building. Where the 3rd floor has been finished the remaining columns rising to the 4th floor will be poured. As these columns are completed, new sections of the 4th floor will be poured.

Looking east from the 4th floor.
Looking west from the second floor.

We don’t have an update on possible Saturday work yet but we will post it when we do. Please check back regularly for updates.

Leave a Reply

Your email address will not be published. Required fields are marked *