Once again rain this week has slowed progress at 158 Front Street East. With the forecast for Halloween consisting of[…]
Read more
Construction information for 158 Front Street East
This site provides construction information and updates for the St. Lawrence Condominium project at 158 Front Street East, developed by Cityzen and Fernbrook Homes.
Once again rain this week has slowed progress at 158 Front Street East. With the forecast for Halloween consisting of[…]
Read moreUPDATE: We have been advised that crews will be on site tomorrow, October 26, from 9 am performing general housekeeping and[…]
Read moreCrews will be on-site at 158 Front Street East, tomorrow, Saturday, October 19, from 9 am through the afternoon. They[…]
Read moreToday, October 16, was a rain day. Some trades were on site but there was no concrete work. The first[…]
Read moreOn Thursday, October 10, the first section of the 4th floor slab was poured at the southwest corner of the[…]
Read moreThere will be crews on-site this Saturday, October 5 at the St. Lawrence Condominiums. They will be taking concrete forms[…]
Read moreWork on the St. Lawrence Condominiums at 158 Front Street East has reached the fourth floor. Work is simultaneously proceeding[…]
Read more