This week the initial stages of work on the third floor of the St. Lawrence Condominiums has begun this week[…]
Read more
Construction information for 158 Front Street East
This site provides construction information and updates for the St. Lawrence Condominium project at 158 Front Street East, developed by Cityzen and Fernbrook Homes.
This week the initial stages of work on the third floor of the St. Lawrence Condominiums has begun this week[…]
Read moreWork is progressing on the second floor at 158 Front Street East. Columns going from the 2nd to the 3rd[…]
Read moreWork at 158 Front Street East this week and into next will continue to focus on forming and pouring the[…]
Read moreWork on the Front Street hoardings and overhead protection is on schedule, with work expected to be completed by the[…]