Work this week has been slowed by yesterday’s rain. Steady progress was made today on work to move the 2nd floor along, and work on the mezzanine and 2nd floor columns.
With rain in the forecast for Thursday, we expect there be some further delays. However, the focus this week remains fixed on making as much progress possible on decking, forming and pouring sections of the 2nd floor.
With the recent holiday weekend and rain delays, crews will be on-site this Saturday, August 10, from 9 am onwards. We expect the work to go no later than mid-afternoon.
If there are any changes of note, we will post and circulate an update. Otherwise our next scheduled post will be on Monday, August 12.