With the ground floor concrete slab complete, this week work is underway to complete the columns that rise from the ground floor to the second floor.
Initial work is also underway to deck, form and pour the second floor concrete slab.
As with the ground floor, this will be done in sections. There is also a small mezzanine level to formed and poured. Work on the second floor will continue throughout this week and next.
We do not anticipate any late evening work this week. If this changes will post and circulate an update. If there is weekend work to be scheduled for July 20, we will also provide an update. Please check back.