With the ground floor concrete slab now complete, work continues to complete the columns rising to the second floor and begin the initial sections of the second floor.
Decking for the second floor work is already in place in the southwest portion of the site. Next week decking, forming and concrete work will continue. The work will generally move from the southwest of the site counter clockwise.
Work will also continue around the ramp area facing Frederick Street.
We will provide a further update on Monday afternoon, July 15.