Midweek Update for 158 Front St. E., May 15, 2019

Work continues on the forming and decking work for the at-grade concrete slab floor at 158 Front Street East.

Today the initial sections of the at-grade slab were poured and finished. Some of these sections will be poured in two phases.

Freshly poured concrete being finished.

The mix of forming, decking and sectional concrete pouring will continue for the balance of the week and into next week. We do not anticipate any evening concrete work at this time.

Concrete truck at the Frederick Street entrance.

There is no work scheduled this coming Saturday, May 17.

The site will be closed for Victoria Day on Monday, May 20.

Our next scheduled update will be posted on Tuesday, May 21 at or before 7 AM.

Leave a Reply

Your email address will not be published. Required fields are marked *