Monday, April 29, weather permitting, the crews on site at 158 Front Street East will be pouring the last piece of concrete floor slab for the P1 level. Concrete finishing may continue into Monday evening, if necessary.
Through the week, crews will continue building suspended decking for the in preparation for the initial Ground Floor concrete pours. However, we expect that concrete pours for the Ground Floor will not begin until the week of May 6.