Work was slowed today, April 23, by rainfall in the afternoon. Otherwise work on the walls and columns rising from the P1 slab floor level continues. Forming has also begun for some of the initial sections of the Ground Floor slab.
Work will progress through the week to complete the walls and columns that support the Ground Floor level. Over the next two weeks forming, pouring and finishing will be underway for the Ground Floor slab itself.

As we have noted previously, concrete finishing may extend into the evening when necessary However, active concrete pouring is expected to be done within standard construction hours.
We will post an update at the end of the week if work is scheduled for Saturday. Otherwise our next update will posted on Monday morning, April 29.