Work continues this week on the P1 floor slab level and the columns that run from the P1 level to what will be the ground floor concrete slab.
This work is being done in stages across the site, in other words section by section, with forming coming first, followed by pouring concrete and then finishing concrete to ensure it sets correctly and has the correct smoothness and is level.
While the goal each day is to complete work within the standard weekday operating hours of 7 am to 7 pm, concrete work may need to continue into the evening in order to ensure concrete sections are correctly finished.
We will post a midweek update on Wednesday afternoon, April 10.