The at-grade slab, the floor of the P3 level, has been completed across the site. For the balance of the week work will continue to complete the columns that run from the P3 level to the P2 level and from the P2 level to the P1 level. Framing and forming the P2 slab level will continue into next week
Update as of March 15
We now have conformation that there will be no work this Saturday, March 15. We have posted an update here.
Our next regular update will be posted and circulated by or before 7 am Monday March 18.