This week concrete work continues on the P2 slab level and the columns that run to the P3 to the P2 levels and P2 to P1 levels. As the weather forecast is mainly milder for the week we do not anticipate major changes to the schedule.
There will be concrete trucks arriving on site throughout the day at both the Sherbourne Street and Fredrick Street entrances.
We will post a mid-week updated on Wednesday, March 13.