Despite the unseasonably cold weather work continues on schedule at 158 Front Street East.
The ‘slab on grade’ AKA the concrete ground floor of the P3 parking level should be complete this week. The lower level of the ramp is also on schedule to be poured this week.

The completion of the ‘slab on grade’ marks a significant milestone in the initial phase of construction.
Once completed this week the focus of work in the coming week will be completing the P2 Level slab the columns and walls from the P2 Level to the P1 Level.

At this time no work is expected on Saturday. If this changes will post and circulate an update.