Tomorrow, Saturday, February 23, crews will be on site to cut the slab that was poured this week. They will also be stripping a few forms that were used for pouring columns. Work will begin at 9 am and should be complete by early afternoon.
Looking ahead to the week of February 25
The start of the week will see regular construction activities get underway again. Forming columns and sections of P3 level and P2 level concrete slab. Concrete trucks will be arriving throughout the work day accessing the site from both the Sherbourne Street and Frederick Street entrances.

Next Update
Our next regular update will be posted on Wednesday, February 27.