Construction Update, February 20, 2019

Work continues for the balance of the week on concrete forming and pouring for the at-grade – P3 – concrete slab, the columns from P3 to P2, and the the P2 concrete slab.

While there is freezing rain and snow in the forecast for today, Wednesday and into Thursday evening and the early morning, it is to clear later the morning. Given this forecast concrete work may be halted or slowed.

If there are significant adjustments to the construction schedule we will post updates here. Otherwise our next post will be Friday with a look ahead to Saturday and next week.