The plan for this week’s construction is to complete as much of the at-grade P3 level concrete slab as possible. The concrete work on site is moving counter-clockwise from the southwest corner of the site to the northwest corner of the site. The columns from the grade level to the P2 slab level are poured after each section of at-grade slab, followed by the forming and pouring the P2 slab.
However, given the weather forecast of extreme cold for Monday morning followed by heavy snow, and then more extreme cold on Wednesday and Thursday, the planned work schedule may be significantly revised. We will post updates here as may be necessary. Please check back through the week for updates.

Assuming weather conditions permit, there will be concrete trucks accessing the site from both the Fredrick Street gate and the Sherbourne Street gate. Since the removal of the excavators on site, there is now additional room on the Frederick Street side of the site for trucks to enter, deliver the concrete and be washed on-site before exiting.
We do note that concrete trucks must continue running, even when they are waiting to enter the site, to ensure the concrete remains fluid. Every effort is made to get trucks on and off the site with as quickly as possible.

We will post details of any work that may be planned for Saturday, February 2, later this week.