This week will see the continuation of excavation and soil removal from 158 Front Street East. Work is also steadily progressing on the forming and pouring of the at-grade lower slab floor and the concrete footings.
There will be concrete work through the week as the P3 level slab continues to take shape.
We will provide an update later this week, including confirmation of work that is planned for Saturday, January 12. Please check back for details.