Saturday December 22, 2018. Look Ahead to January 2019.

There will be excavation work on site at 158 Front Street East this Saturday from 9 am. After Saturday, the site will be closed over the holidays, re-opening on January 2, 2019.

The remaining ramp and driveway will be excavated and the soil removed in the coming weeks to permit concrete and footings to be poured in the northwest of the site.

Looking Ahead

Excavation will continue until the remaining ramp and driveway is cleared to allow the concrete slab at grade, the floor of the P3 parking level, to be continued into the northwest corner of the site.

Pouring the the concrete for the PS level slab floor will resume in the New Year, from January 2, 2019. As will the forming and pouring of footings.

Depending on weather, it is hoped that the first sections of the P2 level floor will be formed and poured by late January or early February. We will proved a more precise update in January.

Our next full update will be posted by or before, 7 am, January 2, 2019.