Saturday work at 158 Front E., December 15, 2018

There will be work on site Saturday, December 15, from 9 am. A crew will be on site excavating on the north side of the site. Trucks will be hauling the removed soil from the site. 

Looking ahead, this coming week will see the first concrete pour for the foundation slab. We will have a more comprehensive overview of next week’s construction schedule posted by or before, 7 am, Monday, December 17. 

If you have questions regarding construction activity please contact us contact@158frontconstruction.info