158 Front Construction Overview for December 3 – 7, 2018

This week at 158 Front Street East the main work will on-site will consist of:

  • Excavating the soil along the north wall of the site.
  • Installing more shoring rakers along the lower level of the north wall.
Shoring ‘rakers’ providing additional support along the north wall of the site. 
  • Continuing with forming and pouring more foundations.
Sections of the initial foundation levels.
  • Preparations for the ground level slab by draining and laying pipe if weather conditions permit. This work is expected to begin in the second half of the week.
Soil on site awaiting removal.

While temperatures are forecast to be close to average for this time of year, rain and snow are possible and this may slow progress at the site. If there are significant weather related changes we will post updates here.

We will also post, no later than Friday, December 7, regarding any possible work on Saturday, December 8.