There will be a crew on-site this Saturday from 9 am. They will be doing some light excavation and soil removal in preparation of next week’s ongoing work on the initial phase of the foundations. Next week will also see the installation of raker shoring on along the north wall of the site to provide additional structural support during the next phase of work.
For an informative article on shoring in construction please see this article: “How Tiebacks, Rakers, and Struts Support Shoring Walls” at Skyrise Cities:
https://skyrisecities.com/news/2016/12/how-tiebacks-rakers-and-struts-support-shoring-walls
We will post an additional overview of next week’s construction by or before 7 am, Monday, November 12.