This week work at 158 Front Street will focus on preparation for the installation of the second crane on site. This crane will be placed on the southeast of the site adjacent the concrete platform.
There will be concrete pouring to make the base that the crane will be anchored to, following the same pattern of the first crane. The installation date for the second crane is set for October 23.
Lighting is scheduled to be installed under the overhead protection. This lighting will replace the existing temporary lighting on-site.
We will update this site if we have updated information on this week’s construction activities. Please check back regularly.