There will be excavation and hauling work on site 158 Front, tomorrow, Saturday, September 15 from 9 am to approximately 4 pm.
The installation of hoardings and overhead protection was delayed a day by Monday’s rain storm. Work on this will resume next week to complete the hoarding along Front Street east and Sherbourne Street.
Our construction overview for the coming week will be posted by or before 7 am Monday, September 17.
If you have questions regarding construction activity please contact us contact@158frontconstruction.info