This week excavation work continues through Friday. Significant progress has been made in the past week, however, excavation will remain the focus of work on site into mid-September.

On the east side of the site, construction of the housing for the temporary electrical supply continues. This wood frame structure will ensure the safety of this high-voltage installation which provides power to the site during construction.

This week the truck access point to the site will remain at the northwest corner of the site, as trucks enter and exit the site from Frederick Street.