This week and over the course of the coming weeks, the focus of work on the site will be bulk excavation in the eastern two-thirds of the property. Excavation will go approximately 3-storeys down from street level.
REVISED truck movement information updated August 10:
The original plan for trucks entering and exiting the site do take away excavated soil has been changed. It has been determined due to negative impacts on timing, traffic and pedestrian flows. Starting this past week, trucks are at the site from King Street East, travelling south on Frederick street, reversing into the site at the Frederick Street gate, then departing from the site, making a right turn onto Front Street and wither continuing on Front or turning north on George and then heading west on King Street, depending on traffic conditions. While this differs from the original routing, it provides for safer and shorter turning into the site, provides less impact on vehicular traffic and reduces the impact on pedestrians using the east side of Frederick Street.
Please feel free to contact us via email at contact@158frontconstruction.info.