This week at 158 Front Street East sees the continuation tie-back installation, excavation work across the site, and forming for the permanent staging platform on the eastern section of the site, adjacent Sherbourne Street. 

Excavation work is making steady progress but is still in its initial phases. Once the staging platform is completed, excavation on the west side of the site will proceed until it reaches 3 full levels below ground. 

Tie-backs are a key part of the support system that ensures the perimeter walls retain their structural integrity during excavation. Drilling is a central part of this installation process, as is the unavoidable noise that accompanies this work. 