158 Front Construction Overview for May 28 – June 1, 2018

This week 158 Front Street East work crews will continue installing tie-backs. Tie-backs are a key part of the support system that ensures the perimeter walls retain their structural integrity during excavation. 

Tiebacks installed to support the perimeter walls.

On the east side of the site, adjacent to Sherbourne Street, crews are continuing installing the steel framing for the concrete staging platform. This platform will provide key work area for nest phase of construction. The concrete platform will be a permanent part of the building, with underground levels being dug out underneath it.  

Staging platform under construction.

Drilling and excavation work also continues this week.  There will be 3 full levels of underground parking in the project, so there remains a significant amount of excavation ahead. 

Drilling rig on site.

Please check back for updates and please feel free to contact us with any construction related questions via email at contact@158frontconstruction.info.