May 22 – 25: Excavation, tieback installation, and staging platform construction at 158 Front St. E.

This past week saw the installation of hoardings and overhead protection along Frederick Street. As we noted last week, fencing along Front Street will remain in place while excavation continues. Prior to cranes being installed on site, hoardings with overhead protection will be added along Front Street East and Sherbourne Street.

Fencing along Front Street East.

This week 158 Front Street East work crews will be installing tie-backs and continuing with excavating the site. On the east side of the site, work will start on the concrete staging platform that will be used to facilitate the next phases of work by providing a flat usable surface for the next phases of construction work. 

Looking west across the site from Sherbourne Street, where the staging platform will be constructed beginning this week.

Please check back for updates and please feel free to contact us with any construction related questions via email at contact@158frontconstruction.info.

Hoarding and overhead protection on Frederick Street looking northeast.

Leave a Reply