Once again this week will see continued drilling along the east side of the site, adjacent Sherbourne Street. Ongoing surface excavation will also occur through the week. The completion concrete jersey barrier installation along Front Street East is also scheduled for this week.

Looking ahead we expect that within the next two weeks the installation of hoardings and overhead protection over the sidewalk will begin. We will post updates once we have more detailed information.

As a reminder, work that causes construction noise may occur between 7 am to 7 pm Monday to Friday. If work is required on Saturdays, it may occur between 9 am to 7 pm. For more information on construction noise and work hours please click here.

Please check back for updates. If you have any questions regarding the construction schedule please email us at contact@158frontconstruction.info